๐Ÿ“ This daily log is to serve a means of communication of relevant information of key details, activities and overall progress.

 

 

11/21/24 โ€“ On Monday, December 2nd all vehicles affected during phase #1 must be out of their original stall by 8am. You can move your vehicle to the temporarily assigned stall starting on December 1st.

12/02/24 – Monday, sunny day and work in the 5th floor for phase 1 started with gridding. All vehicles has moved from there before 8amย  THANK YOU VERY MUCH and relocated temporally to other stalls.

12/03/24 – Tuesday, sunny day and gridding advanced further into the whole phase 1 area. More gridding is expect for Wednesday and pressure washing on Thursday.

12/04/24 – Wednesday, another sunny day and contractor is done with gridding. Tomorrow, pressure washing.

12/05/24 – Thursday, another sunny day and contractor did pressure washing.

12/05/24 – Friday, sunny and contractor finished with pressure washing cleaning.

12/06/24 – Saturday, sunny and floor preparation was done.

12/09/24 – Monday, sunny and sealing application has started.

12/10/24 – Tuesday, sunny in the morning and sealing application has advanced, mid-day rain stop work for the day.

12/11/24 – Wednesday, sunny and sealing application has further advanced.

NOTE: By next week we will be moving vehicles back from Phase 1 to their original stalls and we will have vehicles of phase 2 moving to temporarily stalls. All affected residents will be notified by email and or phone calls starting Friday and next week.ย 

12/12/24 – Thursday, sunny and sealing application has further advanced.

12/13/24 – Friday, sunny and contractor is applying final top coat today and tomorrow.

12/16/24 – Monday and sunny day. Contractor started with gridding on phase 02 areas.

NOTES:

1-This week we will be moving vehicles back from Phase 1 on Tuesday (After 6pm) to their original stalls and we will have vehicles of phase 2 moving to temporarily stalls this Sunday or before. All affected residents will be notified by email and or phone calls starting Friday and next week.

2-Elevator access in the 5th floor will be blocked starting this Wednesday. USe 4th and side fire stairs to get in and out access.

3-Access to a live camera will be available to help the half lane traffic situation on the upper 4th which should start on Monday, Jan. 6th. More details will be provided.ย 

12/17/24 – We are done with phase 1. Please those with temp stall, return to your original stall starting 5pm.

12/18/24 – Sunny and preparation for phase 2 took place.

12/19/24 – Sunny and preparation for phase 2 took place. Temporarily parking assignments has been issued for affected residents on phase 2. Relocation is schedule for Sunday – 22nd.

12/22/24 – Sunday, please affected units for phase 2, relocate your vehicles to the assigned temp stall today.